High School Projects

At the high school level, major improvements include...

  • enhancing safety and security by improving visibility to the main entrance, updating security cameras and PA systems, installing two-way communication systems between classrooms and the main office, and replacing windows, shades, and interior corridor fire doors.
  • updating the learning environment by replacing select ceiling tile, flooring, and classroom cabinets; replacing music room flooring and instrument storage, replacing lockers; adding an outdoor seating area for students outside of the cafeteria; renovating the locker rooms and all restrooms; and expanding the guidance office.
  • updating the infrastructure to improve operating efficiency and student comfort. (Note: air conditioning will be installed at the high school this summer through revenue the school district received from ESSER funds.)

Caro High School Project list

Safety and Security

  • Replace select interior doors, frames, and hardware
  • Install new handrails at corridor ramps
  • Replace the PA system (add a new master console, provide two-way communication between classrooms and the main office, add speakers, and integrate with the clock system)
  • Replace the fire alarm system
  • Upgrade the security camera system
  • Add emergency power for the pool room sump pump
  • Replace select classroom windows and window shades
  • Install signage to identify the main entrance

Learning Environment

  • Renovate and expand the guidance office
  • Add exterior door from the cafeteria to the new outdoor eating area
  • Renovate locker rooms (fixtures, finishes, partitions, and lockers)
  • Renovate restrooms (fixtures, finishes, and partitions)
  • Replace select acoustical ceiling tiles and grid, classroom flooring, and casework
  • Replace music room flooring  
  • Replace instrument storage  
  • Replace lockers
  • Replace instructional technology  
  • Replace select furniture

Infrastructure Improvements

  • Replace piping to improve drainage  
  • Install trap seals in floor drains
  • Replace pneumatic controls with digital controls
  • Install a new sump pump in the basement  
  • Replace boiler
  • Replace pool equipment disconnects  
  • Update interior lighting to LED
  • Replace wall-mounted lighting to LED
  • Connect roof downspouts to storm system

Site Improvements

  • Replace select areas of sidewalks
  • Install a new sidewalk to connect to the building entrance
  • Replace parking lot, driveway, and bus loop paving
  • Expand the high school parking lot to include a new entrance, access drive, and bus loop
  • Construct a new access road to the site
  • Construct a new concrete plaza for outdoor seating outside of the cafeteria

Athletic Facility Updates

  • Construct a soccer field with drain tile  
  • Construct new tennis courts
  • Improve drainage on the baseball field
  • Install drain tile to softball field
  • Construct a paved accessible parking lot at baseball and softball fields
  • Renovate the current bus garage into a weight room/fitness space